|
ENCLOSURE I
[GAO/RCED-97-179R Compliance With Federal Grant Requirements]
Transportation Issues
AIRPORT FINANCING: Compliance With Federal Grant Requirements
Case Study on Northwest Arkansas Regional Airport
Background
New Airport
- Airport has an 8,800-foot runway with full instrument landing system for both runway ends.
- Control tower is sponsor-funded and -operated.
- Terminal has 78,000 square feet.
- Runway's aggregate base has been laid; pavement will be poured in June 1997.
- Airport to open in the fall of 1998.
Background
Total Estimated Cost
- As of January 1997, the new airport's cost was estimated to be $107.4 million.
- AIP will pay almost two-thirds of this cost, with $32.7 million already paid.
Background
Actual and Proposed AIP Costs
| Fiscal year | AIP funds | Purpose |
| 1991 | $ 601,538 | Master plan study |
| 1992 | 0 |
|
| 1993 | 656,904 | Environmental impact statement |
| 1994 | 9,019,075 | Land acquisition and relocation |
| 1995 | 12,371,000 | Site preparation |
| 1996 | 10,000,000 | Site preparation |
| 1997 | 7,000,000 | Landside infrastructure and equipment |
| 1998 | 3,500,000 | Runway, taxiway, and apron construction |
| 1999 | 5,000,000 | Runway, taxiway, and apron construction |
| 2000 | 7,000,000 | Runway, taxiway, and apron construction |
| 2001 | 7,000,000 | Runway, taxiway, and apron construction |
| 2002 | 7,000,000 | Runway, taxiway, and apron construction |
| Total | $ 69,148,517 |
|
Review Questions
- Did FAA follow its process for awarding AIP grants to the new airport?
- Did FAA follow its criteria for issuing the letter of intent (LOI) for the new airport?
- Was the federal share for the new airport's highway connector consistent with other airport connector projects?
- What are the key factors that will affect the new airport's viability?
Results in Brief
Grant Award Process
- FAA followed its grant award process, which allows subjective assessment of needs.
- FAA approved a grant based, in part, on its subjective assessment that the new airport would replace Drake Field as the region's commercial service airport, but
- airlines serving Drake Field have made no firm commitment to use the new airport and
- Drake Field is actively seeking to retain commercial service.
Results in Brief
LOI Criteria
- FAA considered five key LOI criteria but did not demonstrate that two were met.
- FAA has not defined what constitutes a significant capacity enhancement for projects at small airports.
- GAO's concerns on benefit/cost analysis are
- questionable assumptions and data were used and
- information and conditions were not updated for the LOI.
Results in Brief
Highway Connector Funding
- The federal share of funding for the new airport's connector was set at 95 percent by the National Highway System Designation Act of 1995.
- Other statutory provisions allow states to obtain the 95 percent federal share for highway funding based on many factors.
- A comparison with the federal share of funding for other airport connectors could not be made because FHWA does not maintain such information.
Results in Brief
New Airport's Viability
- The viability of the new airport depends on
- how much scheduled air traffic transfers from Drake Field,
- obtaining capital and minimizing financing costs,
- controlling remaining construction costs, and
- the accuracy of projected nonairline revenues.
- Some uncertainty exists with all of these factors.
AIP Grant Awards
FAA's Project Selection Process
- FAA allocates AIP discretionary funds by applying a national priority system:
- projects receiving funding typically fall within a specified priority range and
- projects outside the priority range may still receive funding based on FAA's judgment.
- The new airport received a ranking outside the priority range for funding.
AIP Grant Awards
FAA's Project Selection Process
- FAA chose to fund the project because of
- population growth between 1980-90 at 18.1 percent -- nearly twice the national average,
- constraints at Drake Field (e.g., operating under FAA's waivers, weather, no precision landing approach, and constrained runway expansion), and
- local community and airline support.
- Once approved, future AIP funding is a priority.
AIP Grant Awards
Questionable Assumption Used
- FAA's justification was based on the assumption that the new airport would replace Drake Field as the region's commercial service airport, but
- the city of Fayetteville stated its intent to retain commercial traffic at Drake Field and
- no airline had committed to use the new airport, although some were interested.
LOI for New Airport
Key Criteria for an LOI
- An LOI can be issued only
- to a primary or reliever airport,
- for airside development,
- with financial commitment from the sponsor,
- for projects that significantly enhance systemwide capacity, and
- when the benefit/cost ratio is greater than 1.
LOI for New Airport
Compliance With Key Criteria
- FAA did not demonstrate that two criteria were met.
- First, FAA has not defined what constitutes a significant capacity enhancement for projects at small airports.
- FAA determined that the new airport would add capacity by eliminating constraints affecting Drake Field.
- It is not clear that the added capacity would be a significant enhancement.
LOI for New Airport
Compliance With Key Criteria
- Second, the benefit/cost analysis included questionable assumptions and data and was not updated. For example, it
- assumed a 100 percent transfer of air traffic to the new airport,
- used unverified weather data, and
- was not updated to reflect installation of a new instrument landing system that improves access to Drake Field.
New Airport Connector
Comparison With Other Connectors
- The National Highway System Designation Act of 1995 set the federal share of funds for the new airport connector at 95 percent.
- Other statutory provisions allow a 95 percent federal funding share -- for example, for states with a high percentage of Native American or federal lands.
- A comparison with the federal share of other airport connectors can not be made because FHWA does not maintain such data.
New Airport Connector
Condition of Current Access Roads
- Current access to the new airport is via state highways 264 and 12, which are inadequate for the anticipated increases in traffic.
- Both highways are two-lane roads with narrow lanes and shoulders and sharp curves.
- Highway 264 -- the airport's primary access -- has a higher accident rate than similar highways in the state.
Viability of New Airport
Air Traffic Projections
- Ultimately, the new airport's viability depends on whether projected air traffic is realized.
- Drake Field will compete for commercial traffic.
- No airline has committed to use the new airport, but airlines are evaluating it.
- The new airport's costs exceed Drake Field's ($10 vs. $1.50 per enplanement).
- Airlines will consider operating costs.
- Airlines will consider new market potential.
Viability of New Airport
Access to and Cost of Capital
- Outside financing depends on privately placed and narrowly secured debt:
- below-market bridge loans,
- $29.5 million bond backed by LOI,
- $48.0 million revenue bond, and
- $10.0 million hangar bond (uncertain).
Viability of New Airport
Project Costs & Nonairline Revenues
- The new airport's construction costs are within budgeted levels, but terminal construction has not started.
- Nonairline revenues (e.g., concessions, parking, and tenants) seem reasonable if projected levels of passenger traffic are met.
NWARA | GAO Report | Home
|